India Grid — Monday 12 Oct: 1 status-triggered addition, 1 date fix, 3 backfills outside window

Gridvik — Monday 12 Oct

Monday 12 Oct: 1 status-triggered addition (Reliance Bhogapuram), 1 date fix (CoreWeave 6 Oct), 3 backfills outside window. Deduplicated vs 5 & 11 Oct.
GRIDVIK GRIDVIK MAPPING INDIA'S DATA CENTRE GRID MONDAY 12 OCT 2026

Review window: 28 Sep – 11 Oct · Deduplicated vs 5 & 11 Oct

1 status-triggered addition.
1 date fix. 3 backfills outside window.

Research-only, append-only addendum. Original 48 rows → 5 Oct 52 → 11 Oct 58 → this proposed copy: 62 rows. Only one row was triggered by an October development.

IN-WINDOW ADDITION PRJ-059 — Reliance Bhogapuram–Polipalli 1.5 GW

Not a new October launch. Proposal first reported 28 Apr 2026 (ET). What’s new is 3–7 Oct land status:

• 3 Oct The Hindu: ~50 acres held / ~800 to go
• 4 Oct The Hindu (Collector): 25 of ~855 acres held / ~830 to acquire
• 7 Oct Deccan Chronicle: renewed protest, memo to tahsildar

We keep announcement_date = 28 Apr, October status in notes. Capacity 1,500 MW basis unstated, ₹1.08 lakh cr per G.O. 30 (not DC-only). Announced, no ground-breaking. Confidence 2/3. Keep separate from PRJ-002 Digital Connexion — no parcel crosswalk, do not sum.
Source: The Hindu (Collector) ↗

CORRECTION PRJ-056 — CoreWeave on Taloja 240 MW → 6 Oct

Official CoreWeave newsroom is 6 Oct 2026, Business Wire syndication is 7 Oct 08:00 EDT, DCD 7 Oct says “yesterday Oct 6”. No capacity change — still 3×80 MW tenant deployment, mid-2028 first phase, optional +240 MW excluded. Tenant, not extra on top of PRJ-005/009. Confidence 3/3.

Source: CoreWeave News (6 Oct) ↗

BACKFILL ONLY — OUTSIDE WINDOW

These are not “new this week” — tagged so you don’t headline them as October launches:

PRJ-060 — AM AI Factory Vizag
512 MW, approved 22 Aug 2026 (G.O. 59), >₹31,387 cr, 2yr4mo establishment, no construction. Conf 2/3.
ThePrint/PTI ↗
PRJ-061 — STT GDC Palava
50 MW → ~400 MW planned IT, MoU 16 Oct 2025, ground 16 Mar 2026. Non-additive to PRJ-021. Conf 3/3.
DCD ↗
PRJ-062 — PDG MU2 Navi Mumbai
120 MW IT, 10 acres, DCD first project-specific report 10 Apr 2026 (10 Apr is report date, not exact ground date). Non-additive to PRJ-025’s 210 MW. Conf 2/3.
DCD ↗
7 WE DELIBERATELY DID NOT ADD — YOUR DISCIPLINE PROOF
STT NM 2&3 = 10 Nov 2024 (old) · CtrlS Chandanvelly = 21 Jan 2025 · Pi 3MW = target Oct 2026 not live · Yotta D2 Blackwell = Aug target no commission by 11 Oct · CBRE 200MW H2 = aggregate · Google HC 6 Oct = already in 11 Oct · Trentar schedule 2028/29-30 = conflicts with signed MoU same 6 Oct — held.
Counting rule — do not sum
PRJ-061 non-additive to PRJ-021, PRJ-062 non-additive to PRJ-025, PRJ-056 tenant not extra capacity. No combined MW total published. Bases differ.
View Live Tracker (20-row sample) → Get Full 62-Row Gridfeed — $500/mo
Lineage
Original 48 rows (SHA c8c75bfb…) → 5 Oct 52 rows → 11 Oct 58 rows → 12 Oct proposed 62 rows. Only PRJ-059 was triggered by Oct 3–7 window. Original and 5/11 Oct packages untouched. Verified_date for new rows = 2026-10-12.

Gridvik — Mapping India's Data Centre Grid · Public data only · Not investment advice
Every row has source URL + verified_date + confidence 1–3
Disclaimer · Terms · Privacy

Questions? Reply to this email — hello [at] gridvik [dot] com

You’re receiving this because you subscribed to Gridvik. Unsubscribe anytime via Buttondown footer.

Don't miss what's next. Subscribe to My Awesome Newsletter:
← Newer Unveiled, under construction, or proposed? This week’s India data-centre signals Older → Weekly Grid — 5 Oct 2026 | CEA grid review, CtrlS–Ciena 100 Tb/s, ₹89-cr order; Odisha backfill
LinkedIn
Powered by Buttondown, the easiest way to start and grow your newsletter.