Unveiled, under construction, or proposed? This week’s India data-centre signals

Gridvik — Monday 19 Oct 2026

This week: CapitaLand Chennai 01 unveiled, Colt DCS–RMZ Mumbai 3 under construction, and two different signals from Bihar.
GRIDVIK GRIDVIK MAPPING INDIA'S DATA CENTRE GRID MONDAY 19 OCT 2026

Review window: 12–18 October 2026

Unveiled. Building. Open. Proposed.

Four different project stages appeared in this week’s news. The useful question is not only “how much capacity?”—it’s what has actually happened, and what remains planned.

UNVEILED — NOT YET TENANT-READY CapitaLand Data Centre Chennai 01

CapitaLand unveiled its Ambattur development on 15 October. The project is described as 53 MW gross power, including 34 MW of IT power across 13 data halls, with a dedicated 110 kV substation. It is expected to be tenant-ready by the end of 2026—so an unveiling is not the same as live capacity.

CapitaLand announcement ↗ · BusinessLine ↗

CONSTRUCTION START Colt DCS–RMZ Mumbai 3

Colt DCS and RMZ announced construction of Mumbai 3 on 15 October, after signing the facility’s first hyperscale customer. The project is described as delivering 64 MW

Don't miss what's next. Subscribe to My Awesome Newsletter:
Older → India Grid — Monday 12 Oct: 1 status-triggered addition, 1 date fix, 3 backfills outside window
LinkedIn
Powered by Buttondown, the easiest way to start and grow your newsletter.