October 5, 2026

Weekly Grid — 5 Oct 2026 | CEA grid review, CtrlS–Ciena 100 Tb/s, ₹89-cr order; Odisha backfill

Gridvik · Weekly Grid — Monday 5 Oct 2026

CEA grid review, CtrlS–Ciena 100 Tb/s,
₹89-cr order; Odisha backfill

28 Sep – 4 Oct 2026 · No new DC live this week — 1 network + 1 order + 3 backfilled approvals · 5-min read, all source-linked

In this issue: 0 verified commissioning changes  ·  1 metro network (CtrlS–Ciena, 9 existing sites, 100 Tb/s)  ·  1 supplier award (Interarch ₹89 cr)  ·  3 Odisha proposals backfilled from 23 Sep — our master goes 48 → 52 rows (PRJ-049–052; PRJ-052 is ancillary, no MW).

🔴 What's new — verified this week

28 Sep · Verified

CtrlS + Ciena — five metro networks, up to 100 Tb/s

What: 5 managed optical networks connecting 9 existing CtrlS DCs — Chennai, Hyderabad, Kolkata, New Delhi, Noida — for an unnamed hyperscaler.

Not a new DC campus. No new MW, no capex/date disclosed. 100 Tb/s is network capacity, not power.

Sources: Ciena, 28 Sep · ETDatacenters, 29 Sep · Confidence: High

30 Sep · Verified

Interarch — ₹89-crore building order for unnamed DC

What: Pre-engineered steel building system for a domestic data centre — customer unnamed. ~₹89 cr incl. taxes, ~10 months execution, 15% advance.

Not a named facility. No location/operator/MW in filing — tracked as supplier award only.

Source: BSE filing PDF, 30 Sep · Confidence: High for order terms

🟠 Backfill ledger — Odisha (HLCA 23 Sep, outside this week)

These 27-project HLCA approvals were reported 23 Sep — logged as backfill, not as 28 Sep–4 Oct approvals. None is construction/energized.

#ProjectReported scopeTracker
PRJ-049High Density Data Centre Ltd (Adani Infra) — Naraj*~1 GW, ~₹1,04,550 cr, ~250 acresAppended — announced
*BS says Khordha
PRJ-050SentraForge AI — Puri120 MW, ₹22,634 cr; GVPRAppended — announced
PRJ-051RKD Construction — Cuttack₹1,500 crNA MW
—HCLTech — Odisha (PRJ-042)₹14,257 cr incl. state assistNo new row

🏛️ Policy & Power

CEA grid-stability review — study, not a rule [30 Sep]

CEA committee on DC load behaviour, demand, policy/regulation, cybersecurity. Trigger: Odisha market-purchase concern + West Bengal 200–300 MVA planning. ~17 GW demand by FY2031–32 (reported estimate).

No new tariff/rule published.

Source: Economic Times, 30 Sep

Schneider + NFH — Digital Energy Grid MoU [2 Oct]

Exploratory MoU for open Digital Energy Grid pilots — not DC-specific.

Source: Business Standard, 2 Oct

📊 Financing & Market

• CBRE Q3 — $9.5B is 3-sector total [28 Sep]: Real estate + DC + hospitality combined; DC 57%. Not DC-only capex. ET/PTI

• Axis Bank — double DC lending in 3 years [1–2 Oct]: >₹8,688 cr portfolio, ~12 clients — not a project loan. Bloomberg

📦 What to watch next week

• Odisha HLCA official list (investodisha.gov.in) — Naraj/Khordha + land split
• SentraForge Puri — financial close / ground-break vs “Execution Phase”
• Sify Chennai 130MW (PRJ-028) — Q4 2026 window approaching


📊 Tracker

Free sample (20 rows): gridvik.com/resources.html#tracker · Download CSV
Full feed (52 rows): Gridfeed — request sample
Teaser: Download PDF

How we verify: Every row = source URL + date + confidence 1-3. Approved ≠ construction ≠ energized ≠ operational. See Methodology. Reply with your state/product — we’ll pull that slice.

Explore Free Sample (20 rows)
Request Gridfeed Sample

Gridvik Research

gridvik.com  ·  hello [at] gridvik [dot] com  ·  LinkedIn  ·  X @gridvikhq

Weekly Grid — every Monday, 5 min, source-linked. Public data only. Not investment advice.
You’re receiving this because you subscribed to Weekly Grid via Buttondown. Unsubscribe anytime

Don't miss what's next. Subscribe to My Awesome Newsletter:
← Newer India Grid — Monday 12 Oct: 1 status-triggered addition, 1 date fix, 3 backfills outside window Older → Weekly Grid — 29 Sep 2026 | No new projects, but market numbers just jumped
LinkedIn
Powered by Buttondown, the easiest way to start and grow your newsletter.