Every retro should start with what was supposed to happen

2026-11-20


Every retro should start with what was supposed to happen

November 20, 2026

A retrospective with no stated intent is a mood survey. The Army figured this out fifty years ago, and most engineering orgs still haven't caught up.

Watch a typical program retro. Someone shares a board with three columns: what went well, what didn't, what to try. Sticky notes appear. People vote on them. The loudest complaint gets an owner and a Jira ticket. Everyone leaves feeling like they've done some learning. Two quarters later the same sticky note shows up again, in slightly different words.

What's missing is a baseline. Nobody wrote down what was supposed to happen, so "what didn't go well" turns into opinion against opinion. The team can't tell a bad plan from bad execution, and it can't tell either from bad luck. Poker player Annie Duke calls this mistake resulting: judging a decision by how it turned out instead of by what you knew when you made it. A retro without a baseline is resulting done as a group.

This week makes it timely. Between November 12 and 16, Microsoft 365, the FAA, AWS us-east-1, Chase and United all had visible outages, and Microsoft's final post-incident report is due today. When you read it, notice whether it separates what the system and its operators expected from what actually happened. That separation is where the learning is. Everything else is the timeline.


Deep Dive — Running Meetings & Async Ceremonies: Retros Need a Baseline, Not a Whiteboard

The US Army's After Action Review came out of the combat training centers in the 1970s and 80s, and the Army codified it in A Leader's Guide to After-Action Reviews (TC 25-20, 1993). Its first move is the one most retros skip: what was supposed to happen? Only after the unit has agreed on the intent does it ask what actually happened, why the two differ, and what to sustain or change. The order matters. Comparing against a stated intent turns a complaint session into a gap analysis, and gaps can be explained.

For a senior TPM this changes how the ceremony is built. Three changes do most of the work.

1. Write the intent down before the work starts, not after it ends. The cheapest way to have a baseline at the retro is to record it at kickoff. Marilyn Darling and Charles Parry, who spent years studying how organizations adopted the AAR (see "Learning in the Thick of It," HBR, 2005, with Joseph Moore), found that the strongest users paired every AAR with a Before Action Review: what are we trying to achieve, what will make it hard, what have we learned before that applies, and what will make us succeed? If your milestone plan doesn't already state an expected outcome and the main risks, the retro will have to rebuild them from memory, and memory is generous to everyone in the room.

2. Do the reconstruction async; spend the meeting on the "why." The facts of "what happened" are the cheapest part to collect and the most expensive to argue about live. Before the meeting, ask each workstream lead to write one paragraph: our intent, what happened, and the gap as they see it. Gather these into a single doc and have people read it silently at the start, the way you'd handle a narrative memo. Then spend the whole session on the third question, why was there a difference, because that's where knowledge about the system lives, and you only get it by talking.

3. Stop counting action items as the output. John Allspaw, who spent years making the case that incident analysis is about learning rather than fixing, points out that the evidence of learning is behavior. People who weren't on call show up to reviews on their own. Write-ups get read by people who didn't have to read them. A retro that produces eight tickets and no change in how anyone plans the next milestone has failed, whatever the ticket count says. Steven Deneir put it bluntly for Scrum.org this spring: if nothing changes next sprint, your retrospective failed. His fix is to commit to one visible experiment, not a backlog of good intentions.

There's a leadership angle that's easy to miss. AARs only work when the most senior person in the room goes first and names their own gap: "I expected the vendor contract to be signed by week 3, and I didn't escalate when it slipped." Ivany's account of Army practice for Thayer Leadership makes this point directly: the leader's candor sets the ceiling for everyone else's. If a director opens the review by assigning blame, the session is over before anyone speaks. If they open by stating a wrong assumption of their own, the room starts telling the truth.

At program scope, keep a running gap ledger: one row per milestone with the stated intent, the actual result, the agreed explanation and the change it led to. After three or four milestones, patterns show up that no single retro would reveal. Maybe estimates always slip at the same handoff, or a dependency team is always "almost done," or risks get named at kickoff and then never tracked. That ledger is also the most honest artifact you can bring to a quarterly business review, because it shows leadership how the plan is learning instead of just whether it's green. One caution about AI note-takers: a transcript of the meeting is not a review of the work. Use the tools to put together the "what happened" timeline before the meeting. Don't let them write the "why." That part has to come from people who were there, arguing it out.

Finally, the cadence. The Army runs AARs right after the event, sometimes in the field, in fifteen minutes. Programs tend to batch them into one big quarterly ceremony, by which point the details are gone and people are defending positions. Short, frequent AARs at milestone boundaries beat one long retro every time, both for memory and for how defensive people get.

The test of a good retro isn't the board. It's whether the next kickoff document reads differently because of it.

Try this week. Pick your next milestone and, before work starts, add three lines to its plan: Intended outcome, Biggest expected risk, What we'll check at the end. When the milestone closes, open the review by reading those three lines aloud, and don't let anyone propose an action until the group agrees on why the outcome differed.


Method — The After Action Review (US Army; codified in TC 25-20, 1993)

What it is. A short, structured team debrief built on four questions: what was supposed to happen, what actually happened, why there was a difference, and what we'll sustain or improve next time.

When to use it. At the close of any milestone, launch, incident, migration phase or high-stakes meeting, ideally within a day or two while memory is fresh. It works best for work the team will repeat in some form.

How to run it:

  1. Restate the intent. Read the original goal, success criteria and key assumptions aloud. If they were never written down, agree on them first, and note that gap as a finding of its own.
  2. Reconstruct what happened. Use a timeline gathered in advance (async write-ups, dashboards, chat logs). Stick to observable facts, not judgments.
  3. Explain the gap. Ask why there was a difference, with the most senior person naming their own misjudgment first. Look for causes in the system (information, incentives, tooling, handoffs) before you look at individuals.
  4. Decide what to sustain and what to improve. Name one or two things that worked and must be protected, and one or two changes, each with an owner.
  5. Carry it forward. Put the improvements into the next Before Action Review or kickoff doc, so the learning changes a plan rather than sitting in a wiki.

When NOT to use it. Don't use an AAR where there's an active disciplinary or legal investigation. People can't be candid when their words may be used against them, so keep the learning review separate from any accountability process.

Example: a TPM closing phase 1 of a data-center migration opens with "We intended to move 40% of tier-2 services by October 31 with zero customer-visible incidents. We moved 28% and had one Sev-2. Let's start with why the 12 points didn't move."


Field Notes

November 2026 Outages, Explained — A useful, if vendor-published (Control Plane, Nov 18), timeline of the Microsoft 365, FAA, AWS, Chase and United outages, which keeps confirmed causes apart from company claims and online rumors. It's a model for how a program-level incident summary should separate what's known from what's guessed.

AI Demands More Engineering Discipline, Not Less — Charity Majors argues that with code now cheap, a team's lasting value is shared understanding, evaluation and observability in production. That's an argument for investing in review and learning ceremonies, not cutting them.

Engineering managers who build are pulling ahead — Jay Rungta (LeadDev) makes the case that judging AI-generated work takes hands-on taste. For TPMs, it's a reminder that your retros now need to ask whether the team could tell good output from plausible output.


Events


Reading


"Those who cannot remember the past are condemned to repeat it."

— George Santayana, The Life of Reason, 1905