October 22, 2026

ERCOT Queue Brief: September 2026 report

Quicksand Check · ERCOT Queue Brief

September 2026 report

From ERCOT's September 2026 Generator Interconnection Status report, compared with August 2026. Issue 2026-09 · built October 22, 2026.

27 new requests (11,125 MW) · 48 withdrawn (8,680 MW) · net +2,445 MW · 38 moved forward, 20 of them from study to a signed agreement · 21 requests past their target date · 1,789 active requests

New requests

The largest requests appearing for the first time, as ERCOT lists them. A request is a study position, not a project.

Request · POICountyTypeMW
Brazos Energy Security
28INR0456 · Tap 345 kV (Bus #1048) Tonkawa Switch – (Bus #11050) Dusty R
FisherGas combined cycle3,000
Blue Energy Center - Phase 3 – Steam Stage 2
33INR0007 · Tap 345kV 80286 DULCE7A - 8676 STATIC7A
VictoriaNuclear1,320
Wolf Bone North Energy Center
29INR0354 · TNMP Cowpen 345kV Substation POIB 38044 (4 mile transmission
ReevesGas combined cycle1,174
Blue Energy Center- Phase 1a - Gas
30INR0150 · Tap 345kV 80286 DULCE7A - 8676 STATIC7A
VictoriaGas turbine780
Titus Sienta Solar
26INR0230 · Tap 138kV 1239 Coyanosa - 11238 Blair Lake Sub
PecosSolar502
Black Mountain Briscoe Gas
29INR0397 · ‎23914, Tule Canyon Substation, 345 kV
BriscoeGas combined cycle495
Horizon Ridge Wind
30INR0128 · POIB is 131853 NOTSW_1_8 - the Notrees SW Substation - Proje
WinklerWind407
Longview Wind
26INR0530 · Venturi (Bus #59923)
DawsonWind353
Myrtle Solar Repower
27INR0636 · 42110 Angleton 138kV
BrazoriaSolar314
SunRustler Solar
28INR0520 · 11082 MAVRKDRW_8 138kV
CulbersonSolar301

Withdrawn

Absent from the new report; ERCOT does not publish why. A withdrawal frees study position at that point of interconnection.

RequestCountyTypeMW
Wolf Bone North Energy Center (OLD)
29INR0162
ReevesGas combined cycle1,204
Axis Ridge Wind
28INR0113
SuttonWind392
Sombrero Solar
25INR0057
SchleicherSolar352
Photo Solar 2
25INR0195
UvaldeSolar300
Grapefruit Solar
27INR0118
HidalgoSolar291
Charolais Solar
21INR0380
MatagordaSolar262
Skeeter Solar
29INR0026
JonesSolar251
Lutum Wind
20INR0029
ClayWind242
Razorbill Solar
22INR0244
MatagordaSolar240
Vazlon Solar SLF
28INR0101
La SalleSolar211

Moved forward

RequestCountyMWStage change
Elk Ridge Solar
28INR0114 · Solar
Pecos503in study → signed, security posted
MRR Solar
30INR0053 · Solar
Pecos500in study → signed, security posted
Gregory Power Development SLF
29INR0068 · Gas combined cycle
San Patricio470in study → agreement signed
Paint Rock Wind
27INR0108 · Wind
Concho379in study → agreement signed
Oak Tree Energy Storage
27INR0091 · Battery storage
Lavaca310in study → agreement signed
Gardner Draw Solar
27INR0355 · Solar
Glasscock310agreement signed → signed, security posted
Cenizo Solar
29INR0219 · Solar
Webb301in study → agreement signed
Wisdom Solar SLF
27INR0438 · Solar
Pecos299in study → agreement signed
New Hickory Solar
20INR0236 · Solar
Jackson209approved for energization → approved for synchronization
Caesar Storage
29INR0132 · Battery storage
Borden206in study → signed, security posted

Crowded points of interconnection

POI (as listed)CountiesRequests
Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2Robertson8
Tap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1.Dallas7
Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7BFoard, Wilbarger6
tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2Fisher5
44880 Waterh_POI_5 345kVWharton5
Tap 345kV 5725 PAWNEESW5 - 8164 COLETO7AKarnes5

Schedules slipping

21 active requests (2,640 MW) carry a target commercial-operation date that has already passed without approval for energization; ERCOT keeps the developer's last reported date until it is changed. Most in: Nolan (2), Upton (2), Reeves (2), Palo Pinto (1), Kent (1).

Rules that moved

  • ERCOT paused the Batch Zero study process on Aug 3, 2026 and plans to file its Batch Zero Eligibility Verification Report Dec 10, 2026. ERCOT, Batch Zero Verification and Audit PUCT presentation, Aug 20, 2026
  • PUCT adopted the final large-load interconnection rule on September 18, 2026 (Project 58481), standardizing requirements for loads of 75 MW or more; the draft's non-refundable $50,000/MW fee was dropped in favor of a flat $100,000 study fee, with $50,000 per MW of requested capacity posted as financial security before studies begin. White & Case client alert, Sept 2026
  • The final PUCT rule gives large loads a 24-month grace period spanning the energization schedule. White & Case client alert, Sept 2026
  • On September 21, 2026 the Governor asked TCEQ to suspend issuance of permits sought by data centers until ERCOT finishes its large-load audit and the Texas Water Development Board completes water-impact evaluations. White & Case client alert, Sept 2026
  • All SGIAs executed on or after January 1, 2026 use the updated form approved in PUCT Project 58211. ERCOT notice M-A120125-02

Dates to watch

  • Dec 10, 2026 ERCOT Batch Zero eligibility verification report due to the PUCT
  • Feb 15, 2027 El Paso Electric annual large-generator interconnection window opens
  • Mar 5, 2028 TCEQ Construction General Permit TXR150000 expires (TCEQ renews it)
  • Sep 1, 2029 Tax Code Chapter 312 abatements expire unless renewed

Full tables for every county: quicksandcheck.com/texas. Method: how the counts are made. Every row is from ERCOT's report or the document linked; this brief takes no position on any project or company and is not advice.


You receive this because you subscribed to the ERCOT Queue Brief. Unsubscribe · Privacy · Quicksand Check, Texas

Don't miss what's next. Subscribe to ERCOT Queue Brief:
← Newer ERCOT Queue Brief: October 2026 report
Powered by Buttondown, the easiest way to start and grow your newsletter.