November 2, 2026

ERCOT Queue Brief: October 2026 report

Parcel & Grid · ERCOT Queue Brief

October 2026 report

From ERCOT's October 2026 Generator Interconnection Status report, compared with September 2026. Issue 2026-10 · built November 2, 2026.

44 new requests (17,385 MW) · 67 withdrawn (10,311 MW) · net +7,074 MW · 31 moved forward, 7 of them from study to a signed agreement · 16 requests past their target date · 1,766 active requests

Read online: parcelandgrid.com/brief/2026-10/  ·  PDF of this issue  ·  Excel: every active request, by county  ·  All issues

New requests

The largest requests appearing for the first time, as ERCOT lists them. A request is a study position, not a project.

Request · POICountyTypeMW
Ironwood Energy Center
30INR0106 · 68051 Reata Station 345kV
CallahanGas combined cycle1,485
TempleCloud Gas
28INR0508 · Tap #3414 Temple Switch - #3780 Tower Switch 345kV DCKT Line
BellGas engines1,140
Rattler Combined Cycle Energy Center I
29INR0410 · 345kV 8318 RIOHONDO7A Substation
CameronGas combined cycle991
Rattler Combined Cycle Energy Center II
29INR0415 · 345kV 8318 RIOHONDO7A Substation
CameronGas combined cycle991
Rattler Combined Cycle Energy Center III
29INR0416 · 345kV 8318 RIOHONDO7A Substation
CameronGas combined cycle991
Great Rock Energy Center II
29INR0417 · Tap 345kV 79011 IRONHORSE TO 46020 LIMEST_POI_5 Ckt 18 and 3
LeonGas combined cycle991
Great Rock Energy Center III
29INR0418 · Tap 345kV 79011 IRONHORSE TO 46020 LIMEST_POI_5 Ckt 18 and 3
LeonGas combined cycle991
BM Freestone Energy Center II
29INR0419 · Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Br
FreestoneGas combined cycle991
BM Freestone Energy Center III
29INR0420 · Loop Big Brown E to Navarro Ckt 1(PTI#3380-68091) and Big Br
FreestoneGas combined cycle991
Ironwood Energy Center II
30INR0107 · 68051 Reata Station 345kV
CallahanGas combined cycle742

Withdrawn

Absent from the new report; ERCOT does not publish why. A withdrawal frees a study position at that point of interconnection.

RequestCountyTypeMW
Ross Solar
26INR0155
RefugioSolar1,026
Ross Storage
26INR0156
RefugioBattery storage511
Sendero Solar
28INR0043
StarrSolar503
HyFuels Calhoun Solar
26INR0028
VictoriaSolar302
Roseland Solar
20INR0205
FallsSolar254
Roseland Solar II
22INR0506
FallsSolar254
Little Ridge Storage
25INR0238
CollinBattery storage252
Black Hawk Solar
28INR0040
DuvalSolar251
Clutch City Solar Phase II
25INR0330
BrazoriaSolar251
Hill Valley BESS
26INR0285
GrimesBattery storage246

Moved forward

RequestCountyMWStage change
Sitges Wind
28INR0017 · Wind
Motley600in study → signed, security posted
Sequoia II Solar
22INR0262 · Solar
Callahan417signed, security posted → Approved for energization
Funston Solar
29INR0015 · Solar
Jones351signed, security posted → Approved for energization
Drake BESS
25INR0101 · Battery storage
Collin257signed, security posted → Approved for energization
Tall Saddle Solar
27INR0309 · Solar
Kenedy252in study → agreement signed
Star Dairy Storage
25INR0334 · Battery storage
Lamar205agreement signed → signed, security posted
Tidwell Prairie II Batt
22INR0503 · Battery storage
Robertson204signed, security posted → Approved for synchronization
Trenno BESS
27INR0173 · Battery storage
Johnson203agreement signed → signed, security posted
Willow Beach Wind
25INR0494 · Wind
Brazoria202agreement signed → signed, security posted
Dry Creek Solar II
27INR0488 · Solar
Rusk201in study → signed, security posted

Crowded points of interconnection

Substation (PSS/E bus)CountiesRequestsMW
Navarro (68091) 345 kVNavarro, Freestone, Ellis247,854
Solstice (60404) 345 kVPecos, Reeves2313,000
RILEY7A (6101) 345 kVWilbarger, Wichita, Foard229,880
Tnp One (39950) 345 kVRobertson, Milam203,794
Cruce (80079) 345 kVDuval, Jim Hogg, Starr195,800
San Miguel (5901) 345 kVDuval, Wilson, Atascosa195,234
Elm Creek (5133) 345 kVWilson, Gonzales, DeWitt194,695
Brown (1444) 345 kVBrown, Coleman, Mills194,694

Schedules slipping

16 active requests (1,900 MW) carry a target commercial-operation date that has already passed without approval for energization; ERCOT keeps the developer's last reported date until it is changed. Most in: Upton (2), Reeves (2), Kent (1), Harris (1), Castro (1).

Rules that moved

  • ERCOT paused the Batch Zero study process on Aug. 3, 2026 and plans to file its Batch Zero Eligibility Verification Report Dec. 10, 2026. ERCOT, Batch Zero Verification and Audit PUCT presentation, Aug. 20, 2026
  • PUCT adopted the final large-load interconnection rule on Sept. 18, 2026 (Project 58481), standardizing requirements for loads of 75 MW or more; the draft's non-refundable $50,000/MW fee was dropped in favor of a flat $100,000 study fee, with $50,000 per MW of requested capacity posted as financial security before studies begin. White & Case client alert, September 2026
  • The final PUCT rule gives large loads a 24-month grace period spanning the energization schedule. White & Case client alert, September 2026
  • On Sept. 21, 2026 the Governor directed TCEQ to pause permits related to data center projects; on Oct. 19, 2026, TCEQ told the Governor it had paused all permits related to building infrastructure directly supporting data centers. TCEQ letter to Gov. Abbott, Oct. 19, 2026
  • All SGIAs executed on or after January 1, 2026 use the updated form approved in PUCT Project 58211. ERCOT notice M-A120125-02

Dates to watch

  • Dec 10, 2026 ERCOT Batch Zero eligibility verification report due to the PUCT
  • Feb 15, 2027 El Paso Electric annual large-generator interconnection window opens
  • Mar 5, 2028 TCEQ Construction General Permit TXR150000 expires (TCEQ renews it)
  • Sep 1, 2029 Tax Code Chapter 312 expires unless continued: no new abatement agreements after that

Full tables for every county: parcelandgrid.com/texas. Method: how the counts are made. Every row is from ERCOT's report or the document linked; this brief takes no position on any project or company and is not advice.


You receive this because you subscribed to the ERCOT Queue Brief. Unsubscribe · Privacy · Parcel & Grid, Texas

Don't miss what's next. Subscribe to ERCOT Queue Brief: