WOAH! J&As — Nov 16: Navy cites unusual and compelling urgency: USNS Guadalupe engines at risk of catastrophic failure
1. Navy cites unusual and compelling urgency: USNS Guadalupe engines at risk of catastrophic failure
DEPT OF THE NAVY (DEPT OF DEFENSE) · Vigor Marine, LLC · value redacted · 10 U.S.C 3204(a)(2)
Posted 2026-11-14, award N3220526C1230, “USNS GUADALUPE FY26 Mid-Term Availability”
The justification says a competitive buy would need a procurement lead time of 381 days, while the vessel's engines are in the 80,000-hour overhaul window and face a "severe risk of catastrophic failure." It puts the cost of delay at $210,167.00 per day.
“engines if not overhaul now will have a severe risk of catastrophic failure based on prior history and risk analysis.”
— Redacted JA.pdf, p. 1
“The vessel’s per diem rate is $210,167.00 per day, which is the estimated losses to the Government for each day of delay.”
— Redacted JA.pdf, p. 2
SAM.gov notice · Redacted JA.pdf
All new notices (4)
- ★ Navy · USNS GUADALUPE FY26 Mid-Term Availability · Vigor Marine, LLC · value redacted · 10 U.S.C 3204(a)(2) · SAM.gov
Modifications to Vigor Marine contract for USNS Guadalupe mid-term availability repairs, justified by unusual and compelling urgency for regulatory compliance. - Consumer Product Safety Commission · Specialized office renovations · EMCOR Government Services · $436,996 (total) · GSAR 538.7104-3(b)(1)(ii) · SAM.gov
Sole-source specialized office renovations at GAO building by EMCOR, as the only capable GSA contractor, to avoid delays. - Defense Health Agency (DHA) · Sole Source: Iradimed 3880 Non-Magnetic Patient Monitor System · SAM.gov
Sole-source purchase of Iradimed 3880 non-magnetic patient monitors for Tripler MRI patient monitoring, citing only one source available. - Federal Aviation Administration · NOTICE OF INTENT TO CONTRACT WITH A SINGLE SOURCE: LEV VORTAC Electrical Power Service… · SAM.gov
FAA intends single-source contract with Entergy Louisiana for new electrical service to LEV VORTAC facility.
Vendor, value and authority are shown only where the AI extraction found them with a quote checked against the document; blank means not extracted yet or not stated, not none. The one-line summaries are AI-written from each notice's text and are not quote-checked.
WOAH! J&As: new federal J&As (justifications for contracts awarded without full and open competition) posted on SAM.gov, all listed above, with the most remarkable few picked out by Claude, via the federal-ja-documents dataset. 4 new notices reviewed today (first collected Nov 14 01:15 ET to Nov 16 01:16 ET).
Chosen and written up by Claude. Quotes are checked word for word against the documents, but check the source before relying on anything. How it works.
Archive & RSS: https://woah-jas.abigailhaddad.com · Subscribe: https://buttondown.com/abigailhaddad